Equipment Calibration Upgrades

Equipment Calibration Upgrades Client: Haleon. Location: Waterford, Ireland. Project Scope Summary: Structural stainless steel support design to enable pulldown calibration of various tanks and equipment. The design had to take into account the dimensions of the calibration Globeweigh equipment and also provide an ergonomic and safe design for the users. We surveyed the existing supporting […]

Detached Dwelling – Cork City

Detached Dwelling – Cork City Project description: Project consisted of the design and construction of a detached 3 storey dwelling located in Cork city.   Scope: ServStream’s scope on the project was as follows: Initial design development for the site. Preparation of planning application including required drawings, documentation, site and newspaper notices. Liaising with local […]

Residential Development – Cork City

Residential Development – Cork City Project description: The project included the design development of a terrace of three houses in Cork City.   Scope: ServStream’s scope on the project was as follows: Initial design development Preparation of architectural drawings Preparation of planning application drawings and documentation Liaising with the local authority including requests for further […]

Fire Protection Project

Fire Protection Project Client: Leo Pharma Project description: Firewater infrastructure upgrade works including the construction of an above ground firewater supply tank, pumphouse and associated pipework to supply sprinkler systems and site fire hydrants and also, the construction of a new firewater retention pond and associated pipework Scope: Servstream acted as the client representative for […]

UPS Upgrade

UPS Upgrade Client: Biomarin Project description: The project involved the design, procument and installation of a new rotary UPS unit to replace an existing machine onsite. Scope: Servstream acted as the civil and structural designers on the project responsible for the following: Design of new screen wall foundations, Reinforced concrete slabs & equipment plinths, Design […]

IE2B Expansion

IE2B Expansion Client: Radley Engineering / Eli Lilly Project description: The IE2b project is an extension to an existing manufacturing building including production and plant accommodation over 3 floors, intermediate mezzanine levels and platforms. The project was completed in 2 phases over a 3 year construction period. Scope: Servstream provided Engineering Design & Management services […]

Wet Processing Project

Wet Processing Project Client: Leo Pharma Project description: The development consisted of an extension to the existing pharmaceuticals manufacturing facility a new 2 storey main production building, employeechanging room facilities and fit out of several rooms within existingproduction buildings.  Scope: ServStream acted as the client representative for the civil, structural and architectural (CSA) scope Managed […]