Fire Protection Project

Client: Leo Pharma

Project description: Firewater infrastructure upgrade works including the construction of an above ground firewater supply tank, pumphouse and associated pipework to supply sprinkler systems and site fire hydrants and also, the construction of a new firewater retention pond and associated pipework

Scope: Servstream acted as the client representative for the civil, structural and architectal (CSA) scope

  • Managed the co-ordination of the Civil, Structural & Architectural work package and site QA in conjunction with the project team.
  • Assisted in the management of the project schedule in conjunction with Planners, Project Managers, Sub-Contractors and Consulting Engineers/Architects etc.
  • Managed sub-contractor activities including tracking progress against schedule and manpower levels.
  • Liaised with design team and project co-ordinators to ensure necessary information, as required by construction team, was prioritised where necessary and issued in accordance with the construction schedule.
  • Answered RFIs and reviewed submittals from the CSA contractor.